Project Description: This project would be a Preliminary Engineering Report on the design and construction of two tsunami shelters, one on the west side of town and one on the east side. The two shelters would provide a warm place for residents to stay in the event of a tsunami and would cut down on evacuation times by having a shelter on each side of town.
People/Organizations responsible for completing these steps: Chignik Bay Tribal Council, City of Chignik Bay, Bristol Engineering Services Company
Cost Estimates:
Cost: $276,100
Timeline: 1 year
Funding Partners: FEMA, HUD-Community Block Grant, Denali Commission, EDA
Evaluation Measures:
- Completion design and engineer of two tsunami shelter
- Increased safety measures for residents of Chignik Bay
Key Project Contact:
Name: Debbie Carlson, cbaytc@aol.com, chignikbayadmin@bbna.com, 907-749-4018
Title: Tribal Administrator
Organization: Chignik Bay Tribal Council
Questions about the CEDS?
Contact Kristina Andrew
Economic Development Program Manager
kRandrew@bbna.com