Bristol Bay Information
CEDS Projects
Project Description: The City Council of New Stuyahok would like to purchase windows, plywood, paint, interior/exterior doors, and electrical for the community building where the city conducts business for the community of New Stuyahok.
People/Organizations responsible for completing these steps: City of New Stuyahok
Cost Estimates:
Costs: $150,000.00
Timeline: 1 year
Funding Partners: USDA, EDA, Denali Commission
Evaluation Measures:
- Materials ordered.
- 2-3 temporary jobs created.
- 3-5 new workspaces created.
- Reduced fuel expenses.
- Increased workplace safety.
- Community meeting space created.
Key Project Contact:
Name: Jerry Walcott, cityofnewstuyahok3@gmail.com, 907-693-3171
Title: Administrator
Organization: City of New Stuyahok
Questions about the CEDS?
Contact Kristina Andrew
Economic Development Program Manager
kRandrew@bbna.com