Project Description: The Native Village of Perryville has acquired seafood quota through the Community Quota Entity for harvest of halibut and cod to sell to niche markets.
People/Organizations responsible for completing these steps: Native Village of Perryville
Cost Estimates:
Costs: $250,000 (Feasibility Study and Business Plan) $6.75 – $7.75 million (Design and Construction)
Timeline: 12 – 36 months
Funding Partners: (Feasibility Study) Economic Development Administration
Evaluation Measures:
- Completion of Seafood Production facility
- 20 to 30 new jobs created
Key Project Contact:
Name: Gerald Kosbruk
Title: Council President
Organization: Native Village of Perryville
Questions about the CEDS?
Contact Kristina Andrew
Economic Development Program Manager